SF’s Van Ness project nearly 2 years behind schedule, millions over budget

By Phil Matier : sfchronicle – excerpt

The $316 million makeover of San Francisco’s Van Ness Avenue is running a year and nine months behind schedule, according to the main contractor, with the completion date now pushed to late 2021.

At the same time, contractors have submitted claims for cost overruns totaling $21.6 million, with more claims likely to come.

“It’s ridiculous. We need better project management both from the contractors and from the MTA,” said San Francisco Municipal Transportation Agency board member Art Torres (more)

Two-mile-long Van Ness bus lane project faces two-year delay

By : sfexaminer – excerpt

The two-mile-long Van Ness Bus Rapid Transit project is facing an almost six-month construction delay.

Piling onto other recent delays, the latest setback will stretch the service’s debut from January 2018 to mid-2020, according to city documents… (more)

The SFMTA doesn’t care about completion. They just want to get their hands on as many streets as possible to tear them all up at once. The more delays the longer they can gridlock the streets. Digging holes is the goal. The public is not amused. Complaints from constituents in all the districts are forcing changes at the SFMTA. The Supervisors may not be able to fix the homeless crisis but they can pressure the SFMTA to listen to us.