Engineers Approve Repair Plan For Transbay Terminal Cracked Beams

Authorities with the Transbay Transit center in San Francisco have approval from an independent expert review panel on their plan of a repair of those cracked beams that forced the center’s closure last year, but the reopening date is still uncertain.

The repair plan, presented last month to the governing board of the authority, involves bolting new steel plates to the top and bottom of the cracked beams.

Christine Falvey, spokeswoman for the Transbay authority, said steel is now on order to complete the repair of the cracks, which NBC Bay Area’s investigative unit reported were caused when crews cut holes into the four inch thick steel in the steel base of the beams… (more)

Steel plates to reinforce cracked beams under Transit Center repair plan

By Laura Waxmann : sfexaminer – excerpt

Plans have been approved to repair fractured beams at the temporarily shuttered Salesforce Transit Center by reinforcing them with steel plates, Transbay Joint Powers Authority officials said Friday.

The repair plans were reviewed and approved last month by a peer review panel of the Metropolitan Transportation Commission, which is also developing recommendations guiding additional inspections at the center prior. No date has been set for the center to reopen… (more)

 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s