Polk Streetscape Construction Update

Only the SFMTA and the DPW would use a construction photograph as a greeting. They must think we appreciate the appearance of the mud and orange cones as much as they do. Guess what, to us ROAD CONSTRUCTION SUCKS! No one except you thinks they look attractive, so quite sending us these hideous photos of broken streets in your cheerful greetings. You are looking a head to spending more of our tax dollars disrupting our lives. We are NOT! How tacky can you get.

29463164-24ff-4fa9-9a8a-d1854bdc42d5.jpg
Water work on North Point Street, January 11, 2017 – San Francisco Public Works

9b48ec82-e298-4bfd-85f6-f6ff3bfb7911.jpgJanuary 13, 2017
Greetings Polk Street Community Member and Happy New Year!
View the latest construction information for the Polk Streetscape Project. Project Activity Summary – Crews have resumed work in segment 5 on North Point Street, between Van Ness Avenue and Larkin Street performing water main replacement work.

Week of January 16, 2017
Crews will continue water main replacement work on North Point Street from Van Ness Avenue to Larkin Street. Work will resume Tuesday January 17, 2017.

Week of January 23, 2017
Crews will continue water main replacement work on North Point Street from Van Ness Avenue to Larkin Street.

Anticipated construction schedule for Segment 5:
Water work: 01/02/17 – 03/27/17
Concrete Flatwork: 01/09/17 – 02/01/17
Final Grind & Pave: 03/31/17 – 04/03/17

Anticipated construction schedule for Segment 4:
Sewer work: 11/2016 – 04/2017
– Bay to Greenwich
– Filbert to Union
Water work: 01/2017 – 04/2017
– North Point to Bay (16″ Main)
– North Point to Chestnut & Chestnut from Van Ness to Polk (8″ Main)
– Lombard to Filbert (8″ Main)
Concrete Flatwork: 04/2017 – 09/2017
Electrical work: 04/2017 – 05/2017
Final Grind & Pave: 09/2017 – 10/2017

Looking Ahead: Construction for the Polk Streetscape Project is anticipated to be completed in six segments over a 24 month period. Construction in segments 5 & 4 are currently underway, with segments 3, 6, 2 and 1 pending. Work for the Polk Traffic Signal Upgrade Project (Contract No. 2568J) is anticipated to begin January 2017 and will occur at nine intersections from Union to Post streets in segments 4, 3 and 2. We will be working closely to coordinate construction activity in these segments.

Polk Streetscape Project – Things to Know… (more)

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s