Some Problems Plaguing BART Were Built Into System From Start

Design decisions made decades ago at the origin of BART now haunt the system, making it more difficult and more costly to operate, officials with the transit agency say.

Designed at the beginning of the Space Age, the people who built BART wanted an ultramodern transportation system. The first transit system to be built after World War II, the goal was to create a sleek, light and smooth riding system. The hope was to draw people back into public transit – using large, tinted windows, wool seats and carpeting and promising speeds of up to 80 mph.

“It wasn’t too far away from the monorail idea,’’ said Randy Rentschler, spokesman for the Metropolitan Transportation Commission, “where families would go on BART like it was kind of a Disneyland ride — you would get on it was almost luxurious in its feel.”

Luxury may have been built in, but the idea of routine failure was not, said BART Operations Manager Paul Oversier.

“Because in the aerospace business failure equals catastrophe well in our business failure is a fact of life,” he said.

Oversier, who came to BART after helping to run the New York subway system, said that system has a whole different approach. It was built to handle failure.

They have express tracks and local tracks they have crossovers almost between every station,” he said. Crossovers are mechanical and electrical switches that allow trains to be routed around problems. BART’s are few and far between, and, according to Oversier: “the ones that we do have are basically in the wrong locations.”

Not having such switches is most problematic in the core part of the system, from West Oakland to Daly City. Here, four lines with trains running every two and half minutes converge to run in one track in each direction. “Basically, if anything happens in that core part of the system,” Oversier said, “the delays to our passengers ad to other trains propagate very quickly and impact many, many trains.”.

The bottleneck was something the designers did not anticipate, one of many design limitations that now hamstring operators.

“A lot of decisions made 50 years ago about this system really limit what we can do today,” said Tom Radulovich, a 19-year member of the BART governing board. The use of ultra- lightweight aluminum cars gliding along on extra-wide gauge tracks at up to 80 mph, he said, had unforeseen consequences.

“We couldn’t order off-the-shelf rail cars – they had to be custom designed, we had to have them custom made,” he said, referring to the latest order of new train cars expected to come on line as soon as next year. He said the new cars cost nearly double the price of more conventional rail cars, which are made of stainless steel and can be mass produced.

Radulovich says nearly all of BART is one of a kind… (more)

RELATED:
‘No Guarantee’ That New BART Trains Will Fix Problem

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s